Delivering Results
Despite complex site conditions and utility constraints, Choate’s proactive approach ensured anon-target delivery, meeting both budget expectations and schedule goals. Knightdale Gateway stands as a testament to teamwork, ingenuity, and commitment to excellence, positioning Beacon Partners for continued success in this growing market.
Strategic Solutions in Action
The Choate team brought innovative thinking and resourceful problem-solving to site complexities.
High-Voltage Powerline Rerouting
A 40,000-volt electrical line ran directly through the middle of the site – a major constraint to progress. Rather than delay construction, Choate strategically re-phased operations to safely work around the line while grading the site, building a 35-foot retaining wall, installing underground conduits, pulling new wire, and tying into a new switch gear system. Once rerouted, the existing overhead line was safely demolished, all without impacting critical milestones.
Rock Repurposing and Site Stewardship
Excavation revealed 65,000 CY of classified rock, a potential cost driver that became an opportunity. The project team crushed and reused the rock onsite, integrating it into geogrid reinforcement for the retaining wall and balancing the site.